How Much Does Federal Reserve Headquarters Renovation Cost?
Updated on | Researched and reviewed by Alec Pow, Founder & Pricing Investigator
Prices, claims, and calculations checked against 13 cited sources. See our research methodology and corrections policy.
The Federal Reserve’s renovation of the Marriner S. Eccles Building and 1951 Constitution Avenue now carries a Board-approved budget of about $2.46 billion. The Fed’s current project FAQ gives that rounded figure for the two historic Washington buildings. A newly released inspector general report shows why the number climbed so far, and its findings go well beyond inflation or expensive finishes.
The September 2026 evaluation found serious cost-control and governance deficiencies but no reasonable grounds for a criminal referral and no administrative misconduct. The report says the renovation project budget rose from $1.317 billion in February 2020 to $2.381 billion in December 2024, while the construction portion more than doubled from $921 million to $2.018 billion. In January 2026, the construction manager proposed construction costs of $2.135 billion.
The clean price answer is about $2.4 billion to $2.46 billion for the approved project. Inflation, redesign, asbestos, contaminated soil and difficult site conditions mattered, but the inspector general found that contract execution and oversight also left the Fed exposed to higher costs.
Article Highlights
Jump to sections
- The Fed’s public page lists about $2.46 billion as the Board-approved renovation budget.
- The inspector general says the narrower project budget rose from $1.317 billion to $2.381 billion, an increase of about $1.064 billion or 80.8%.
- The construction budget rose from $921 million to $2.018 billion, an increase of about $1.097 billion or 119%.
- Four mechanical, electrical and plumbing packages rose from a $206 million estimate to $694 million in awards. That $488 million gap equals about half of the major construction-cost increase examined by the inspector general.
- The Fed had not established a project-level guaranteed maximum price as of July 2026, four years after construction began.
- The inspector general found management deficiencies, but did not find grounds for a federal criminal referral or administrative misconduct.

How Much Does the Federal Reserve Headquarters Renovation Cost?
The headline figure needs one accounting clarification. The inspector general’s 121-page evaluation distinguishes the renovation project budget from the broader multicycle capital budget. The project itself rose from $1.317 billion in 2020 to $2.381 billion in 2024. The multicycle capital budget reached $2.455 billion, which the Fed now rounds publicly to $2.46 billion.
Construction is the largest moving piece. Its budget rose from $921 million to $2.018 billion. The January 2026 contractor proposal of $2.135 billion was another $117 million, or about 5.8%, above that 2024 construction budget. That proposed figure did not automatically become a new Board-approved budget, but it shows that construction pressure had not disappeared.
The schedule moved too. The 2020 plan expected construction to finish in the second quarter of 2024. By August 2026, completion had shifted to December 2027.
What This is About
This is a two-building modernization, not an office redecorating job. The Eccles Building dates to the 1930s and has never had a full renovation. The adjacent 1951 Constitution Avenue building also dates to the early 1930s and required major rehabilitation before it could be used to consolidate staff now working in leased offices. The work replaces electrical, plumbing, HVAC, fire-protection and other aging systems, removes asbestos and lead, upgrades structural and security features, improves accessibility, restores historic stone and interior spaces, and adds below-grade and site work.
That scope explains why comparing the project with a normal commercial office remodel is weak. It does not explain the size of every cost increase. The inspector general’s new contribution is showing where difficult historic construction ended and avoidable management exposure began.
What the Inspector General Found
The report’s central finding is that the Fed chose a construction-manager-at-risk contract structure but did not use its main cost-control features effectively. The inspector general’s report notes that the Fed did not obtain an initial full construction estimate from its construction manager and did not share a stated cost limitation with the contractor at the outset.
Under a normal construction-manager-at-risk model, the owner and construction manager negotiate a guaranteed maximum price. That shifts part of the risk of overruns to the contractor, subject to agreed exceptions. Here, the contractor was hired in 2022, construction began that year, and the first project-level estimate from that contractor did not arrive until January 2026. By then, more than $2 billion in construction work had already been awarded.
The Fed had set a stated construction cost limitation of $857 million in 2020, but the inspector general found that the construction manager and the owner’s representative were unaware of it. As of July 2026, the project still did not have the project-level guaranteed maximum price contemplated by the contract.
The biggest hidden-price lesson is contractual. The Fed divided nearly all construction into 84 smaller price packages rather than setting an early project ceiling and transferring more cost risk to the construction manager. A legal summary of the report notes that the arrangement came to resemble cost-plus reimbursement, with the construction manager receiving a fee equal to 2.95% of construction work.
By December 2025, 69 of the 84 packages had been awarded. The inspector general found that using many small packages without an upper project limit reduced cost certainty, may have narrowed subcontractor competition, sacrificed some economies of scale and made costs harder to track.
The 2.95% fee also matters because it was not capped by an early project-level guaranteed maximum price. As a scale illustration, 2.95% of $2.078 billion is about $61.3 million. That is not a separate claim that exactly $61.3 million was paid as profit or fee. It shows why a percentage-of-construction fee deserves a ceiling when the underlying construction total is still rising.
Where the $960 Million Increase Went
The inspector general compared $1.117 billion of March 2022 architectural and engineering estimates with $2.078 billion in awarded construction packages and change orders through December 2025. The gap was about $960 million. Seven cost categories accounted for $799 million, or about 83%, of that increase.
| Construction category | 2022 estimate | Actual award cost | Increase |
|---|---|---|---|
| Plumbing and HVAC | $107 million | $346 million | $239 million |
| Electrical | $91 million | $252 million | $161 million |
| Earthwork | $49 million | $158 million | $109 million |
| Wood, plastics and composites | $16 million | $110 million | $94 million |
| Metals | $32 million | $104 million | $72 million |
| Masonry | $41 million | $108 million | $67 million |
| Concrete | $65 million | $122 million | $57 million |
| Total of seven categories | $401 million | $1.200 billion | $799 million |
Mechanical, electrical and plumbing work was the largest concentration. Four MEP packages were estimated at $206 million in March 2022 and were eventually awarded for $694 million. The $488 million difference represents about 50.8% of the $960 million increase examined in this comparison.
One mini case is especially sharp. Two core-and-shell MEP packages were estimated at $178 million but awarded for $539 million, a difference of roughly $362 million. Each received only two bids even though the contract called for at least three. The Fed did not ask its outside construction representative to independently validate those prices before award.
Inflation did raise construction costs, and the inspector general did not dismiss it. The dispute was about scale. The inspector general found that inflation, asbestos remediation, design changes and other project conditions contributed to higher costs, while weak cost controls also played a role.
The inspector general compared the awards with the Producer Price Index for new office building construction. That index rose about 16% from March 2022 through October 2023, while the two core-and-shell MEP packages were 203% above the March 2022 estimate. By June 2025, the relevant PPI had risen about 19%, while two interior fit-out MEP packages were 454% above their earlier estimate.
The report also found that the seven largest cost categories increased by 88% to 588%, while the new-office-building PPI rose 24% from March 2022 to January 2026. The Board told the inspector general that a broad national index can be a poor measure for one complex Washington project. The inspector general agreed that local and project-specific factors matter, but concluded that inflation alone did not account for the size of the gap.
Management failures were not the only cause. The project faced real construction problems. The Fed says the work uncovered more asbestos than expected, contaminated soil and a higher-than-expected water table, while the buildings required new plumbing, electrical, fire-protection and HVAC systems. A 2025 Board budget document transferred $572 million into the Eccles-1951 program while canceling unused funding for the separate New York Avenue renovation.
Design decisions also added cost. The inspector general found that a January 2023 change from a mostly open-office layout to a mostly closed-office layout required extensive redesign of interior MEP systems and parts of the core-and-shell work. The redesign pushed final interior design completion back by 21 months.
The Luxury Features
Political criticism focused heavily on marble, water features, a garden terrace and an elevator described in design documents as private. The inspector general examined those items and found they did not materially drive the cost increase. The Fed’s 2021 plans had already included the disputed features before later budget increases, and the Commission of Fine Arts approved the final design in September 2021.
The inspector general found a proposed total of about $3.4 million for water features before the new 1951 fountains were removed, an estimated $615,000 for vegetated roofs, $6 million for atria scaffolding and $27.6 million for skylight work. The masonry package totaled $107.9 million, but that category covered far more than new marble. Project staff said 87% of the marble would be restored material and 13% new.
The elevator also predates the renovation and serves several floors. Fed officials said staff can use it, while the governors’ floor remains security-controlled. The report did not tie it to the major cost increase.
Similar Problems Before
The strongest governance finding is that this was not the first warning. The Fed’s earlier Martin Building renovation grew from $203 million in 2012 to $454 million when it finished in 2022 and took 11 years. A 2014 inspector general audit had already warned that the Martin project lacked a contractual stated cost limitation and recommended establishing one quickly.
A later 2021 renovation-management audit called for clearer governance, required project-planning components and stronger control of schedule changes. The 2026 inspector general report says several of the Eccles-1951 problems closely resembled those earlier findings.
The recurrence matters because the Board had already been told to improve cost estimates, cost ceilings, governance and status reporting on another major renovation.
What Happens Next
Current Fed Chair Kevin Warsh accepted the inspector general’s recommendations and brought in the General Services Administration as project executive. GSA said on October 1 that it would help manage the remaining renovation with a focus on cost discipline and completion.
The Fed also plans a full audit of project costs to test whether services paid for were received and whether credits or reimbursement should be pursued. The inspector general’s seven recommendations include setting a completion cost and schedule metric, fixing or negotiating the construction manager’s fee, auditing awarded costs, reconciling contracted services with services received, and adopting a stronger governance framework for future large projects.
The legal question has moved separately. On October 2, the Justice Department said it would not reopen the criminal investigation of former Chair Jerome Powell based on the current record. That is consistent with the inspector general’s finding that it lacked reasonable grounds for a criminal referral. It does not erase the inspector general’s project-management findings or prevent further financial audit work.
The renovation is not funded through a normal congressional construction appropriation. Section 10 of the Federal Reserve Act authorizes the Board to assess the Reserve Banks for its expenses and for buildings, and states that those assessment funds are not appropriated moneys.
Reserve Banks transfer excess earnings to the Treasury after expenses when remittances are positive. Building costs are capitalized over time, so the project is not a one-year congressional check or a simple dollar-for-dollar reduction in one year’s Treasury receipts.
Related Federal Project Costs
The renovation is easier to interpret beside other federal capital projects with disputed scope and funding. The White House East Wing modernization cost separates privately funded ballroom work from taxpayer-funded support infrastructure. The Kennedy Center renovation cost shows how appropriated repair money and competing construction plans create several legitimate budget figures.
The Reflecting Pool renovation cost separates early estimates from identifiable contract value, while the White House utilities renovation shows why infrastructure spending should not be reduced to visible finishes.

Answers to Common Questions
How much does the Federal Reserve headquarters renovation cost?
The Fed currently lists about $2.46 billion as the Board-approved budget for renovating the Eccles and 1951 Constitution Avenue buildings.
How much did the project originally cost?
The inspector general says the renovation project budget was $1.317 billion in February 2020, while its construction component was $921 million.
Why did the cost increase so much?
Inflation, design changes, limited subcontractor bidding, asbestos and contaminated soil all contributed. The inspector general also found that the Fed failed to use several contract cost controls, did not set a timely guaranteed maximum price and had weak internal project governance.
Did the inspector general find criminal wrongdoing?
No. The inspector general found no reasonable grounds requiring a federal criminal referral and no administrative misconduct, despite identifying serious project-management deficiencies.
When will the renovation be finished?
The current construction schedule runs through December 2027. GSA has now been brought in as project executive for the remaining work.
Disclosure: Educational content, not financial advice. Prices reflect public information as of the dates cited and can change. Confirm current rates, fees, taxes, and terms with official sources before purchasing. See our methodology and corrections policy.